Rain delays Brownton road construction

$
0
0

It has been the story of the summer, projects delayed because of the rain.
The Brownton City Council heard that the road construction project is behind schedule due to all the rain in June at its meeting on July 3.
The construction crew is behind on street work and cannot continue with the underground work until they get caught up, according to John Rodeberg from Short Elliot Hendrickson Inc. (SEH).
R&R Excavating of Hutchinson, requested a four week extension for completion of phases one and two of the project.

Read the full story in the July 11 edition of The Chronicle.